Option 1 — Car Park 2 Siting

Women's Centre Ventilation

Crane and staging area sited within Car Park 2, with no road closures required throughout the works.

Option 1 — crane location, staging area and parking relocation zone, Car Park 2
Crane location, staging area and parking relocation zone — Car Park 2
Disabled spaces
0
Standard spaces
−68
Pros
No tower oversail with load
Both entrances stay open
No mitigations needed at Level 1 entrance — clinical pathway unaffected
Site circulation maintained
East road access maintained
No road closures required
Lower safety risk profile
Cons
68 standard parking spaces lost through the works
40 disabled (DDA) spaces require relocation
Extended footprint at rig/de-rig — total loss of Car Park 2
Possible need for temporary offsite parking
Proximity to neighbouring properties

Programme

Crane programme
Site impact
UK summer holidays (approx.)
Crane 1
Crane 2
27→28 Jul rig 20:00→06:00
8→9 Sep de-rig 20:00→06:00
25→26 Nov rig
22→23 Dec de-rig
Crane erected
Peak impact — rig/de-rig night
Impact while crane on site
No impact — crane off site
UK summer holidays (approx.)