Option 2 — East Road Siting

Women's Centre Ventilation

Crane sited to require oversailing the occupied tower, with entrance closures and diversions during rig/de-rig.

Option 2 — crane location, oversail zone, staging area and access closures
Crane location, oversail zone and staging area, with rig/de-rig road and entrance closures
Disabled spaces
0
Standard spaces
−19
Pros
Significantly reduced loss of car parking spaces
Retains more parking for staff, patients and visitors
Smaller ground-level footprint
Cons
Oversailing the occupied tower raises the impact of a dropped load — likelihood rated low by the crane operator (refer to risk register)
East entrance closed during rig/de-rig
Mitigations needed at Level 1 entrance to maintain the clinical pathway
Emergency and patient access diverted to south entrance during rig/de-rig
Road closures required during rig/de-rig
Relocation of shoreline ambulance charging points required
Extended footprint at rig/de-rig for crane positioning to build the jib of the 450t crane — c.19 additional parking spaces lost

Programme

Crane programme
Site impact
UK summer holidays (approx.)
Crane 1
Crane 2
27→28 Jul rig 20:00→06:00
8→9 Sep de-rig 20:00→06:00
25→26 Nov rig
22→23 Dec de-rig
Crane erected
Peak impact — rig/de-rig night
Impact while crane on site
No impact — crane off site
UK summer holidays (approx.)
See how this plays out on site Maximum footprint at rig/de-rig, the standing condition while erected, and the resulting access arrangements — in sequence.
Sequence of Impact