✕68 standard parking spaces lost through the works
✕40 disabled (DDA) spaces require relocation
✕Extended footprint at rig/de-rig — total loss of Car Park 2
✕Possible need for temporary offsite parking
✕Proximity to neighbouring properties
Programme
Crane programme
Site impact
UK summer holidays (approx.)
Crane 1
Crane 2
27→28 Jul rig 20:00→06:00
8→9 Sep de-rig 20:00→06:00
25→26 Nov rig
22→23 Dec de-rig
Crane erected
Peak impact — rig/de-rig night
Impact while crane on site
No impact — crane off site
UK summer holidays (approx.)
See how this plays out on siteMaximum footprint at rig/de-rig, the standing condition while erected, and the resulting access arrangements — in sequence.